Annual Report 2007  



Refining and Petrochemicals

The total refining budget amounted to US$282 million, 62% higher vs. 2006, which led allowed for execution of 95 reconversions, growth, equipment replacement, and environmental projects  

In 2007, progress was made to position the Barrancabermeja and Cartagena refineries in the first quartile in Latin America by the year 2010.

It is worth to highlight in this area’s society management the startup of operations of the Cartagena Refinery S.A. in April, the fulfillment of the volumetric plans, the load increase, the reduction of environmental incidents, the increase in refining gross margins, the consolidation of cash flow benefits in the optimization plan, and the increase in value added, EVA.

Refinery loads

Petroquimica y Refineria

The results of loads to both refineries exceeded the forecasts. With regard to Barrancabermeja, the goal set for the year 2007 was accomplished, which included the general shutdown of the U-2000, and the difficulties undergone by the U-250 were overcome.

As regards Cartagena, 80.3 thousand barrels of oil per day (Kbpd) were refined, that is to say, the maximization scheme of unit load was maintained. This value becomes the highest ever reached in the refinery.

Refining gross margin

Petroquimica y Refineria

The refining gross margin was favored by the crack spread, (term that represents the calculation of earnings or profitability), the enhanced performance of valuable products, and the optimization of processes and crude yields at the refineries.

The increased margin was derived from high international prices caused by the high demand from countries like China and India, and to the increased production of medium distillates in
Barrancabermeja, which increased by 3% and helped reduce diesel imports to thus meet the domestic demand.

Total operational unit costs

The total operational unit cost increased vis-à-vis previous years.
This was affected mostly by the exchange rate, which was 11.4%
below budget, the non-availability of natural gas that led to its substitution
for more costly fuels such as LPG or Fuel Oil, and the
price of natural gas, which was raised in the Cartagena refinery.

Pretroquimica y Refinación

An additional aspect that affected the total cost was the depreciation and amortization, as the Cartagena Refinery was given to the new Society Refinar S.A. Worth to highlight are the reduced costs of chemicals and catalysts derived from best practices addopted by the refinery optimization program, added to the reduced use of electrical power in Barrancabermeja, as a result of the improved reliability of industrial services.

Reliability

The utilization factor was affected in the Barrancabermeja refinery by the reduced load to cracking resulting from the medium distillates optimization strategy. There was also a reduction in Cartagena caused by more days of unscheduled shutdowns, which affected mainly the catalytic cracking unit.

Accidentality

Petroquimica y Refinación

Accidentality rates in our refineries have been reduced in recent years as a result of leadership, safety visits, “3 Wh’s” methodology, and personnel awareness campaigns intended to make safety a priority.

The recording of environmental incidents started in the year 2005. Improvement has been evidenced as a result of an increased interest on the environment and its preservation.

Investment

The total Refining and Petrochemicals investment budget amounted to US$282 million in the year 2007, 62% higher than 2006, and 100% higher than 2004. It included 95 reconversions, growth, equipment replacement and environmental projects.

As per the investment budget breakout, it is worth noting that US$172 million were allocated to the fuel hydro-treatment project, US$28 million to projects intended to increase polyethylene production, US$22 million to propylene production (US$13 million in Barrancabermeja and US$9 million in Cartagena), US$5 million to diesel blending, US$4 million to Consolidated Operational Control (COC), and US$4 million to environmental projects.

During this period, US$1.5 million were destined to studies for the Industrial Services Master Plan of the Barrancabermeja Refinery, which gave rise to this project, with an estimated value of US$300 million and duration of 30 months.


Ecopetrol is the operator of the Cartagena Refinery where it has a 49% of the property


credits top Annual Report
© 2008 ECOPETROL S.A. Derechos Reservados.
Bogotá D.C. Edificio Principal Cr 13 No. 36 - 24
Conmutador 2344000 - Fax 2344099
 
Colombia es pasión
TLC
Gobierno en Línea
Alca
Colombiemos
Ministerio de Comercio, Industria y Turismo